Acceptance criterion

Definition adopted by the guide

A verifiable condition specific to one item.

CPM-E guide, Appendix A, page 109

Assessed in the Certified Product Manager Enterprise, domain 5: Prioritisation, backlog and delivery.

In detail

Definition and purpose

An acceptance criterion is a verifiable condition specific to one item. The CPM-E guide adds its practical purpose: resolving ambiguity in the item's wording. See the acceptance criterion glossary entry.

The key words are verifiable and specific. The condition must allow verification, and it must clarify the particular item rather than state a general delivery rule. When reviewing an item, ask: which part of its wording could be interpreted differently, and what condition would resolve that difference?

Where it matters in practice

Acceptance criteria matter when ambiguous wording could produce a delivery that the team considers correct but the requester considers wrong. The guide identifies unresolved ambiguity before starting as a major source of delivery rework.

Do not confuse a missing criterion with a missing item. If an otherwise well-formed item needs one line to clarify its meaning, add that line. The guide explicitly says that the item should not return to the queue merely because that clarification is missing.

Distinguish neighbouring terms for CPM-E

The definition of done separates delivered from not delivered and applies to every item. An acceptance criterion resolves ambiguity for one item. An ordering criterion serves a different purpose: it declares why one item sits above another.

For study, keep these questions separate: what condition clarifies this item, what conditions apply to every delivery, and what rule explains the order of work? Use these distinctions when preparing for the Certified Product Manager Enterprise certification.